The first strategy of the 2008 Downtown Plan was to enhance the image of downtown.  Like many other areas of town, continual improvement and maintenance projects are needed to accomplish this.  Recent and planned projects include:

Downtown Improvements List (Phasing Plan 2014)

Roadways:
  • Repairing Central Avenue from 14th to 15th Streets (2013)
    • 1st Avenue South & 12th Street
    • 1st Avenue South and 13th Street
    • 12th Street and 2nd Avenue South
  • Reconstructing 1st Avenue North and 3rd to 7th Streets (April 2014)
  • Reconstructing and realigning 1st Avenue South from 4th to 10th Streets (2014 - 2015)
Brickwork:
  • Crosswalk at County/Willie Moe's (Spring 2014).
  • Crosswalk at 7th (2014-15).
  • Crosswalk repair on Central  (2013).
  • Crosswalk repair at Central & 13th (2013)
  • Comprehensive sidewalk brick repair on Central Avenue (on-going).
  • 5-year Capital Improvement Plan for Downtown lists potential projects through 2015.
Parking:
  • Reconstruction of another public parking lot in 2014.
  • Public parking lot sign at 1 - 2 parking lots in 2014.
  • Downtown Public Parking lots are typically cleaned early Wednesday mornings.  
  • As revenue increases in the City's parking fund other projects may include:
    • Identifying a schedule to improve more public parking lots.
    • Continuing identification of downtown public parking lots (signage).
    • Continuing phased installation of on-street parking meters.
    • Installing public parking lot signage throughout the downtown and at each public parking lot.

Wayfinding Signs:

  • Signage along Central Avenue (2014).
  • Information kiosk at 9th & Central Avenue (2013 or 2014)

Lighting:

  • Streetlights on the Square (within library/park) sandblasted, painted black & cleaned (2013).
  • Streetlights on the Square (outside perimeter, along streets) sandblasted, painted black & cleaned (2014)

Completed Projects:

Roadways:

  • Resurfacing of 1st Avenue North from 7th to 10th Streets (2010)
  • Slurry seal to extend the life of the pavement:  (2012)
    • Central Avenue from Square to 12th Street
    • 3rd Street between 1st Avenue North and 2nd Avenue South
    • 12th Street between 1st Avenue South and 4th Avenue South
  • Curb repair at:  (2012)
    • 8th Street and Central
    • 6th Street and Central
    • 11th Street and 1st Avenue North
  • Manhole adjustments - raising to meet street elevation and make a smoother roadway (2012)
    • Central Avenue
    • 1st North and 13th
    • 3rd Street and 1st Avenue South
    • 3rd Street and alley behind Doyle Construction

Brickwork:

  • Crosswalk, intake and sidewalk leveling on 9th Street 1st Avenue North through Central Avenue intersection.  Crosswalk repair at 8th Street (south crosswalk and southeast curb and gutter repair) and Central Avenue (2011).
  • Sidewalk brick repair at 6th Street and Central Avenue intersection (2012).

Parking:

  • Reconstruction of Lot 1 (Brass Monkey) in 2012.
  • Public parking lot sign at Lot 1 (2012).

Contact Us

Communications
City Hall
819 1st S Ave
Fort Dodge, IA 50501
Get Directions

  • Phone: (515) 576-4551
  • Staff Directory
  • Office Hours:
    Monday - Friday
    8:00 A.M. to 4:30 P.M.

Stay Connected:

Facebook Twitter Click to Take A Video Tour of Fort Dodge