Click here for an update from the City Engineer about our current construction projects.
Below is general information about a few of the City of Fort Dodge's current construction projects:
Name: Community Sewer Initiative - Southeast Sewer Trunk/G10 & M05 Basin
Area: S 16th St at 8th Ave S, 8th Ave S to S 18th St, S 18th St to 12th Ave S
Description: Remove and reconstruct roadway and utilities
Started: Jan 2016
Expected Completion: Fall 2018 - Project is substantially complete. Site clean-up, reseeding, and tree planting will occur in the fall to allow for better grow.
Engineering Firm: McClure Engineering Contractor: Wicks Construction
Contractor Bid Amount: $3,184,718.08
Funding Sources: Sanitary Sewer Fund
Name: Community Sewer Initiative - Southeast Sewer Trunk/G10 & M05 Basin - Phase 2
Area: 12th Ave S from S 18th St to S 23rd St and S 23rd St from 12th Ave S to 13th Ave S
Description: Remove and reconstruct roadway and utilities
Started: Spring 2018 Expected Completion: Spring 2019
Engineering Firm: McClure Engineering Contractor: Crow River Construction
Contractor Bid Amount: $3,369,489.30
Funding Sources: Sanitary Sewer Fund
Name: 24th Ave N Construction
Area: 24th Ave N from N 15th St to Williams Dr
Description: Construct street and utilities on new 24th Ave N from N 15th St to Williams Dr
Started: April 2017 Expected Completion: Fall 2018
Architecture Firm: McClure Engineering Contractor: Rasch Construction
Contractor Bid Amount: $1,152,579.50
Funding Sources: Jurisdictional Transfer and Tax increment Financing
Name: East Region Storm Sewer - Phase 3B
Area: 1st Ave S at S 29th St
Description: Improvement of storm sewer utilities, sidewalks, and street
Started: Spring 2018 Expected Completion: Fall 2018
Engineering Firm: Snyder & Associates Contractor: Wicks Construction
Contractor Bid Amount: $2,685,627.30
Funding Sources: Storm Sewer Bond, TIF, State & Federal Grants, LOST, Jurisdictional Transfer Funds
Name: N 1st St Bridge Replacement
Area: N 1st St Bridge over Soldier Creek
Description: Replace bridge and relocate trail
Started: Summer 2018 Expected Completion: Spring 2019
Engineering Firm: Calhoun-Burns & Associates Contractor: Christensen Bros
Estimated Project Cost: $1,023,647.05
Funding Sources: State Grants, LOST
Name: 2018 Street Repair Project
Area: Click here for details
Description: Mill and overlay section of streets with some sidewalk, curb and gutter replacement
Started: Summer 2018 Expected Completion: Fall 2018
Engineering Firm: City Engineer's Office Contractor: Fort Dodge Asphalt
Estimated Project Cost: $1,206,036.17
Funding Sources: LOST
Name: 2018 PCC Patch Project
Area: Click here for details
Description: Remove and replace failing patches of concrete
Started: Spring 2018 Expected Completion: Fall 2018
Engineering Firm: City Engineer's Office Contractor: Castor Construction
Estimated Project Cost: $442,793.00
Funding Sources: LOST
Name: South Central Drainage Improvements – Phase 1
Area: Between 14th and 15th Aves S from S 24th to S 29th St
Description: Install new storm sewer and streets in the area
Started: Summer 2018 Expected Completion: Fall 2018
Engineering Firm: Snyder & Associates Contractor: Rasch Construction
Contractor Bid Amount: $1,372,327.00
Funding Sources: Storm Water Utility, GO Bonds
Name: Community Sewer Initiative – Collection System - Phase 2
Area: Various
Description: Line sewer services and seal up manholes
Started: Spring 2018 Expected Completion: Fall 2018
Engineering Firm: McClure Engineering Contractor: Municipal Pipe & Tool
Estimated Project Cost: $1,912,422.30
Funding Sources: Sanitary Sewer Fund